top of page

Update for the week of August 26 to 30

Projet Portage à Grand-Sault

Update for the week of August 26 to 30 on the Portage Road project:

  • Continued installation of sanitary sewer line on Portage Rd.

  • Continued installation of storm sewer pipe on Portage Rd.

  • Continued installation of water mains on Portage Rd.

  • Sub-base spreading at the intersection of West River Rd. and Portage Rd.

 

Work scheduled for this week:

  • Finalizing the installation of the sanitary sewer line, storm sewer line and drinking water line on Portage Rd.

  • Preparing to transfer residents to the new main lines

  • Paving and sidewalk work on the section between boul. Broadway and Chapel Street and on Portage Rd.

 

Comments


bottom of page