Update for the week of June 24 to 28 on the Portage Road project:
Continued installation of sanitary sewer line on ch. Portage
Continued installation of storm sewer line on ch. Portage
Continued installation of water mains on ch. West River
Installation of sanitary sewer manhole
Installation of temporary water line on 2nd project sector
Work scheduled for this week:
Continue installation of sanitary sewer line on ch. Portage
Continue installation of storm sewer line on ch. Portage
Continue installation of water mains on chemin Portage and chemin West River
Connect the two water mains at the Portage/West River intersection
Visit https://www.grandsault.com/en/portage for all updates.
Comentarios