Update for the week of September 3 to 6 for the Portage Road project:
Finalization of sanitary sewer line, storm sewer line and drinking water line installation on Portage Rd.
Transfer of residents to new main lines
Paving and sidewalk work on the section between boul. Broadway Blvd. and Chapel Street and on Portage Rd..
Work scheduled for this week:
Pouring of concrete curbs and gutters on Portage Rd.
Paving and sidewalk work on the section between Broadway Blvd. and Chapel Street, and on Portage Rd.