Update for the week of September 3 to 6

Projet Portage à Grand-Sault

Update for the week of September 3 to 6 for the Portage Road project:

  •  Finalization of sanitary sewer line, storm sewer line and drinking water line installation on Portage Rd.

  • Transfer of residents to new main lines

  • Paving and sidewalk work on the section between boul. Broadway Blvd. and Chapel Street and on Portage Rd..

 

Work scheduled for this week:

  •  Pouring of concrete curbs and gutters on Portage Rd.

  • Paving and sidewalk work on the section between Broadway Blvd. and Chapel Street, and on Portage Rd.